Kangcheng power generation factory quality inspection
Yangzhou Kangcheng power generation equipment Co., Ltd. solemnly promises that every diesel generator set will go through a number of tests before leaving the factory:
1、Controller filling system
2、Connect the starting battery
3、Connect oil tank: oil inlet, oil return
4、Add antifreeze to water tank
5、Connect test load
6、Controller Startup Test
7、Load test: the no-load, 25%, 50%, 75%, 100% and 110% power sections need to be tested for 5 minutes respectively. After passing the quality inspection, the certificate will be stamped with the qualified seal, and the tester will sign before loading the logistics and transporting the goods to the freight station.
Kangcheng power generation - national standard
GB/T 2819-1995 General specification for mobile power station
GB/T 15548-1995 General specification for three phase synchronous generator driven by reciprocating internal combustion engine
GB/T 2820.1-1997 Three phase synchronous generator set driven by reciprocating internal combustion engine
Part 1: use, rating and performance
GB/T 2820.3-1997 Three phase synchronous generator set driven by reciprocating internal combustion engine
Part 3: alternator for generating set
GB/T 2820.5-1997 Three phase synchronous generator set driven by reciprocating internal combustion engine
Part 5: generator set
GB/T 2820.6-1997 Three phase synchronous generator set driven by reciprocating internal combustion engine
Part 6: Test methods
GB4712-90 《Classification requirements of automatic diesel generator》
GB12786-91 《General technical standard for automatic diesel generator set》
ISO8528-1 《Reciprocating internal combustion engine driven alternator》
GB/T 1029-1993 Test method of three phase synchronous motor
GB/T 1993-1993 Cooling method of rotary motor
GB/T 7409.1-1997 Definition of excitation system for synchronous machines
GB/T 7409.2-1997 Model for power system research of synchronous motor excitation system
GB 10068.1-1998 Vibration measurement method and limit vibration measurement method for rotating electrical machines
GB 10068.2-1998 Vibration measurement methods and limits of rotating electrical machines
GB10069.1-1988 Noise measurement method and limit noise engineering measurement method for rotating electrical machines
GB10069.1-1988 Noise measurement method and limit noise simple measurement method of rotating electrical machines
GB10069.1-1988 Noise measurement methods and limits of rotating electrical machines
Kangcheng power generation - solemn promise
1、Yangzhou Kangcheng power generation equipment Co.,Ltd.solemnly promises:guarantee the new original power according to the contract requirements,guarantee the quality of the original power,impose a penalty of 10 for one fake,and resolutely do not use small power to impersonate large power.All the above commitments are written into the contract,and we guarantee that the clients'prosecution against us is unlimited and never expired.
2、Yangzhou Kangcheng power generation equipment Co., Ltd. solemnly promises: our company can assist customers who need to identify the authenticity and real power of diesel generator set. The identification result of local after-sales service station of diesel engine brand shall prevail, and the customer shall contact the identification matters, and the cost shall be borne by Kangcheng power generation.
3、Yangzhou Kangcheng power generation equipment Co., Ltd. solemnly promises: 7 days no reason for return, 24 hours after-sales online, all units lifelong tracking service.